PROJECT OVERVIEW:
The Project involves the construction of in-situ pits, stormwater pipes, and driveways for properties, along with milling and re-sheeting of roads, and conducting line marking.
PROJECT SCOPE:
Install 170 linear meters of RMS SO Kerb using slip form.
Complete 190 linear meters of Stormwater Drainage, including 3 out of 8 modified cast-in-situ pits and a 600mm diameter pipe.
Construct access driveways for properties.
Undertake deep lift asphalt pavement and conduct Mill and Resheet Works.
Implement line marking.
Execute landscaping works.