Gore Hill Data Centre 33Kv Supply

status

Status

Completed

client

Client

Ausgrid

location

Location

Artarman, NSW

PROJECT OVERVIEW:

The project involves installing new conduits to link existing distribution panels to an external pit for future supply needs. Tasks include nondestructive excavation, installing 150mm conduits, and connection pits, backfilling with TSB, installing protection bollards, and permanently restoring the area.

PROJECT SCOPE:

  • Install 180 linear meters of 150mm conduits, 63mm UGFO conduits, and a spare 63mm conduit.
  • Backfill the designated area with TSB and conduct permanent restoration through the use of hot mix asphalt and concrete works.
  • Installation of protection bollards.
  • Altering the existing pits to fit new conduits and building a new Pit.
  • Minor restoration and concrete cleaning in a transformer bay and bus bar area.